Activity data: the consumption
Manual — Energy Management · chapter 3 of 13
Everything in the module starts here: the energy, the emissions, the indicators and the reports use the same consumption, month by month, by facility and by energy carrier. A facility is each H2O site.The consumption table
Section titled “The consumption table”
Figure 5. The Consumption tab of the activity data.
- 1The period (From and To) and the Facility. Left blank, it shows all the facilities you reach.
- 2The Consumption, Entries and Variables tabs.
- 3The totals for the period: energy, emissions, cost and how many entries are still to approve.
- 4The matrix: one row per facility and energy carrier, in the energy carrier unit; the Total row is in energy.
- 5Missing flags a month already closed with no data, on a row that has had data before.
- 6Download spreadsheet exports the matrix.
- 7The consumption split By energy carrier, By facility and By end use.
| Where the month’s number comes from | Rule |
|---|---|
| Entry | the Approved or To approve entry counts; the Rejected one does not |
| Main meter | counts when there is no entry for that energy carrier in the month |
| Submeter | does not add up; it only splits the consumption by end use |
Entering the month’s consumption
Section titled “Entering the month’s consumption”- Click New entry.
- Choose the Facility, the Month and the Energy carrier.
- Enter the Quantity and, if it differs from the default, the Unit.
- Optional: the Cost, the document number, the supplier and the invoice file. For electricity, demand, peak and off-peak also appear.
- Click Save.

Figure 6. The New entry form.
- 1Facility, Month and Source (invoice, manual reading or estimate).
- 2Energy carrier, Quantity and Unit. H2O converts to the base unit of the energy carrier.
- 3End use, when the entry is for a single use, and the Cost.
- 4The billing period and the invoice Attachment.
- 5Save. The entry starts as To approve.

Figure 7. The Entries tab.
- 1Spreadsheet template and Import spreadsheet, to load many entries at once.
- 2The filters by Status and by Energy carrier.
- 3An entry To approve, with Approve and Reject.
- 4An Approved entry. To correct it, use Reopen.
An entry To approve already counts in the totals, and the table shows how many there are. Whoever approves checks the number against the invoice; rejecting asks for the reason and takes the entry out of the count.
Loading the history by spreadsheet
Section titled “Loading the history by spreadsheet”The baseline of an indicator needs at least twelve months. To avoid typing month by month, load the history by spreadsheet.
- On the Entries tab, click Spreadsheet template. The file already comes with the columns and two example rows from your company.
- Fill in one row per facility, month and energy carrier. The columns period (in YYYY-MM format), carrier and quantity are mandatory.
- Click Import spreadsheet and choose the file.
| Column | What it accepts |
|---|---|
| entity_id or entity | the number or the exact name of the facility; blank = the facility you are in |
| period | the month, YYYY-MM |
| carrier | the code (electricity, natural_gas, diesel…) or the name of the energy carrier |
| quantity and unit | the quantity, with a comma or a point; the unit is optional |
| cost, end_use, document, supplier, origin, notes | optional |
Variables: production, sales and weather
Section titled “Variables: production, sales and weather”Consumption alone says little: a plant that produces more uses more. The variables are the numbers that explain the consumption, and it is with them that H2O calculates the baseline (chapter 6) and the energy intensity.

Figure 8. The Variables tab.
- 1Spreadsheet template and Import spreadsheet, for the history of the variables.
- 2New variable.
- 3Each variable with the facility, the type and the unit.
- 4The value for each month. Click the cell to type.
| Type | Example | What it is for |
|---|---|---|
| Production | tonnes, parts, occupied beds | baseline and specific consumption |
| Sales | the month’s revenue | Energy intensity (energy over sales) on the dashboard and in the annual report |
| Weather | degree days | air-conditioning baseline |
| Area, Occupancy, Distance | m², people, km | baseline for buildings and fleets |